Climate & Disasters · Report · File No. 261115-066
Grid watchdog says data centers have added $29.4 billion to power costs for 67 million
The independent watchdog for the largest U.S. power grid says demand from data centers, many of them not yet built, drove up costs that customers in 13 states and Washington, D.C., will pay. It warns that a December auction could add $5 billion to $10 billion more.
Every quote in this story (6) was matched word for word against its source. How we work

The independent watchdog for the nation's largest regional power grid said this week that demand from data centers has caused "an irreversible increase of $29.4 billion" in costs for all customers 1. That grid, run by a company called PJM Interconnection, serves 13 states and Washington, D.C. Its costs reach the electric bills of 67 million people 2.
The watchdog is Monitoring Analytics, PJM's official independent market monitor, led by Joseph Bowring. It released its report on Nov. 12, covering January through September of this year 1. The report says the total will keep growing. A power auction set for December is expected to add another $5 billion to $10 billion in data center costs to bills across the region 2.
What the watchdog found
PJM runs two main markets. One buys electricity for use today. The other, called the capacity market, pays power plants years ahead of time to be ready for the hottest and coldest days. Capacity costs make up about one-fifth of total wholesale electricity costs 2.
The report found the everyday energy market was competitive this year. But Bowring said the capacity auctions held for the years 2025 through 2029 were "not competitive, primarily as a result of the inclusion of forecast demand for data centers" 1. In other words, PJM's forecasts counted large computer centers that have not been built, and that pushed prices up 2.
From Channel GOPShapiro says he sued Trump 19 times, wonJosh Shapiro · 212 plays · captioned, with the source named
The full wholesale cost of power on the grid rose from $79.19 to $111.61 per megawatt-hour, an increase of 40.9 percent over the first nine months of 2025. A megawatt-hour is 1,000 kilowatt-hours, the unit on a home electric bill. Capacity costs alone rose 81.1 percent 1. The monitor estimates that without data centers, the wholesale cost would have been $101.66, meaning data centers added $9.95, or 9.8 percent, through capacity costs alone 1.
The $29.4 billion comes from four auctions that have already been held. They cover power for June 2025 through mid-2029: $9.33 billion for 2025-26, $7.27 billion for 2026-27, $6.50 billion for 2027-28 and $6.27 billion for 2028-29 3. The figure is the monitor's estimate and includes both existing and forecast data center demand. It does not count any effect on energy or transmission prices 31.
We are continuing to get closer and closer to a reliability crisis and an affordability crisis.
A December auction could add billions more
PJM's next capacity auction, for 2029-2030, is scheduled for Dec. 9 to 15 3. The monitor expects it to clear at the highest price allowed 2. It recommended putting off the auction until forecast data center demand can be taken out, and it wants data centers to bring their own new power plants so they stop pushing costs onto other customers 13.
PJM's federal regulator, the Federal Energy Regulatory Commission (FERC), rejected a special "reliability backstop auction" that PJM had proposed to match data centers with power plant builders. FERC also rejected much of PJM's plan for big customers that do not bring their own power. PJM has filed revised plans, but the special auction will not happen before December 2.
The grid is also short on reserve power. In July, PJM fell 6,800 megawatts short of its target for standby capacity 2.
The White House promises
The Trump administration has made two well-publicized promises on this issue. In February, it adopted a statement of principles with the governors of the PJM states that was meant to protect households and small businesses from data center costs. That agreement is not binding. Separately, under a "Ratepayer Protection Pledge," the administration and major tech companies agreed that the companies would get their own power supplies 2.
The watchdog says PJM has not put into practice the rule at the heart of both promises: that data centers should pay their own costs 1. PJM spokesman Jeffrey Shields disagreed that PJM controls how those costs are split. He said that decision belongs to state utility regulators and that PJM's proposals give states clear ways to charge the costs to data centers 2. "PJM recognizes the impacts of rising wholesale costs on regular people and businesses," Shields said 3.
The pattern is clear. Promises that were announced at the White House have not stopped the bill from growing. The concrete protection customers have now came from a lawsuit.
Where Democrats stepped in
Pennsylvania Gov. Josh Shapiro, a Democrat, sued PJM in late 2024 after a July 2024 auction hit a record $269.92 per megawatt-day. A settlement capped auction prices at $325 per megawatt-day 4. Later auctions cleared right at that cap 2. In February, PJM agreed to extend the cap through the 2029-2030 auction, the one scheduled for December. Shapiro said that would save PJM customers an additional $27 billion 4.
Pennsylvanians can't afford higher prices
In New Jersey, Democratic Gov. Mikie Sherrill signed a Data Center Fair Share law on July 7. It requires large data centers to pay their share of energy costs. On the same day she signed two other bills meant to cut utility costs, and all 3.6 million New Jersey ratepayers are getting a $25 bill credit 5.
Today, we're putting money back into people's pockets while holding utility companies and large data centers accountable
That matters because the cap limits how high the price can go, but it does not take data centers out of the math. If forecast data center demand stays in December's auction, the monitor expects the price to hit the ceiling again 2.
Jon Gordon of Advanced Energy United, a clean energy industry group, said fixing PJM's rules is "taking longer than anyone wanted or anybody hoped" 2.
not competitive, primarily as a result of the inclusion of forecast demand for data centers
The Record
- Gov. Josh Shapiro's office announces PJM has agreed to extend the $325-per-megawatt-day price cap through the 2029-2030 auction, which he says will save customers an additional $27 billion 4.
- New Jersey Gov. Mikie Sherrill signs a Data Center Fair Share law requiring large data centers to pay their share of energy costs 5.
- Utility Dive reports the monitor's midyear finding that data center demand made up 9% of PJM's wholesale power price through July 6.
- PJM's independent market monitor reports that data center demand has caused an irreversible $29.4 billion increase in capacity costs 1.
- PJM's capacity auction for 2029-2030 is scheduled to open, running through Dec. 15 3.
Republish this story on your site or in your newsletter
Any site, blog or newsletter may run this story free of charge. Keep the credit line and its link to the original, do not sell it, and edit only for length or house style (the full terms). Photos carry their own licenses, noted under each photo on this page, so use the text alone unless a credit says otherwise.
Paste it into your editor's HTML view. The one-pixel image at the end tells our newsroom the story ran; it stores no reader data.
Sources
- Monitoring Analytics via PR Newswire, “Market Monitor Finds PJM Wholesale Electricity Markets Competitive” (2026-11-12). prnewswire.com/news-releases/market-monitor-finds-pjm-wholes
- Pennsylvania Capital-Star / WITF, “Electricity grid watchdog warns of higher prices after delayed PJM market reforms” (2026-11-13). witf.org/2026/11/13/electricity-grid-watchdog-warns-of-highe
- Energy News Beat, “PJM's Monitor Put $29.4 Billion on Data-Center Load. The Policy Fight Is Who Pays Next.” (2026-11-14). energynewsbeat.co/electrical-generation/pjms-monitor-put-29-
- Pennsylvania Capital-Star via Yahoo News, “Grid operator PJM agrees to extension of wholesale electricity price cap” (2026-02-13). yahoo.com/news/articles/grid-operator-pjm-agrees-extension-1
- ROI-NJ, “Sherrill signs bills for ratepayer relief, along with holding utility companies and data centers accountable” (2026-07-08). roi-nj.com/2026/07/08/industry/energy-utilities/sherrill-sig
- Utility Dive via Yahoo Finance, “Data center load made up 9% of PJM wholesale costs so far in 2026: market monitor” (2026-08-27). finance.yahoo.com/energy/articles/data-center-load-made-9-09
Found an error? Tell the newsroom. Corrections are noted at the top of the story.
More from the files
Power bills are on Tuesday's ballot as nine states elect utility regulators
Voters in nine states will choose officials who help decide what households pay for electricity. Democrats could win control of Georgia's board, while Arizona's 14% rate request may be decided before any winner is sworn in.
Pennsylvania Democrats' new trifecta puts early voting and faster mail counts on the table
Democrats won the Pennsylvania Senate and kept the governor's office, giving them full control of state government. That could end years of gridlock over how the state runs its elections, including mail ballots, early voting and voter ID.
Shapiro urges Democrats to make stopping Medicaid and SNAP cuts a first move in 2027
Pennsylvania's Democratic governor says the new Congress should first reverse cuts to Medicaid, food aid and Affordable Care Act help. A Trump veto and a Jan. 1 start for Medicaid work rules limit what Democrats can do.
Delivered free to your door*
The Morning Edition
One short email at 7 a.m. Eastern: the day's top files, one clip worth your time, and the race to watch. Plain English, large type, no clutter.
*Your inbox. Free. Unsubscribe with one click, any time.